LLC “UST-POKSHENGA LPH” WILL INCREASE THE HARVESTING VOLUME UP TO 800 THOUSAND M³ PER YEAR BY CONSTRUCTING AN ALL-YEAR-ROUND PONTOON CROSSING VIA THE YULA RIVER

LLC “UST-POKSHENGA LPH” WILL INCREASE THE HARVESTING VOLUME UP TO 800 THOUSAND M³ PER YEAR BY CONSTRUCTING AN ALL-YEAR-ROUND PONTOON CROSSING VIA THE YULA RIVER

LLC “White Sea Timber Floating Company” (“BSK”, a member of Titan Group) is now upgrading an 800-ton barge into a pontoon crossing for the logging company LLC “Ust-Pokshenga LPH”. The crossing will be built via the river Yula (one of the biggest inflows of the Pinega river) at Pinega district of Arkhangelsk region.

The project was launched in 2018 under the Titan Group investment program.

LLC “White Sea Timber Floating Company” will tow the pontoon crossing in May 2019 – this is the only month a year, when it is possible to perform such operation.

The barge upgrade is in progress under the Russian River Register supervision.

The pontoon will be equipped with massive ramps withstanding the load up to 100-ton, which allows heavy timber carriers to use the crossing. The crossing throughput capacity is over 300 thousand m³ of timber annually.

All the works are carried out to the approved schedule.

Installation of the all-year-round pontoon crossing allows increasing the harvesting volume for LLC “Ust-Pokshenga LPH” up to 800 thousand m ³ per year.